Monday 26 April 2010

Project Update (26/04/2010)

The following Gantt chart shows the project progress to date. The circuit has been completed, and the program has been successfully tested (though will require calibration in the morning before the assessed test).


The build has been completed and successfully tested, though the rear caster wheel was discovered to cause drag which resulted in the buggy veering off course. It was decided to test an alternative wheel design which was also successfully tested and, in the morning once new batteries have been sourced, the best design will be neatly installed. The progress of the buggy has extended fully into the project buffer, though is due to be completed on schedule.