Monday, 26 April 2010

Meeting 7 (26/04/2010)

At this point the lead programmer confirmed she had completed the program testing to a satisfactory standard having taken timer advice from me, with just final calibration experiments necessary. The buggy chassis had been marked out to design; drilled; and cut to shape by the build team, and the final assembly had been completed.

The final test in this meeting however proved the caster wheel at the rear of the buggy caused an unacceptable level of drag due to its weight and off centre pivot. This will require redesigning tomorrow morning before the assessed test, in order to maximise the operational ability of the buggy.

The electronics specialist and assistant project manager have the majority of the images and videos of the construction phase for this project. These shall be posted shortly, along with a detailed explanation of the design and assembly process.

After the test, all group members shall post retrospective reports about this project, including how successful they believed it to be and what future changes they would make to improve the buggy if they were to do it again.

Thursday, 22 April 2010

Meeting 6 (21/04/2010)

The final design was discussed and finalised. Build and program test schedule has been set and is due to be completed by Friday 23/04/2010.

Tuesday, 23 March 2010

Meeting 5 (23/03/2010)

This meeting was held in the lab and during this time the PICAXE program was finalised and tested. The circuit was built and tested utilising a breadboard.

Members discussed the construction of the buggy and the build team completed the final design.

For the next meeting members are required to source remaining materials and solder the strip board. Members will also post all relevant material to the blog, including design research, final designs, component lists, and explanation of the rational behind these choices.

Thursday, 18 March 2010

Meeting 4 (18/03/2010)

Progress made on programme and requires testing. An initial prototype will need to be built during the lab of the 23rd March, where the programme can be tested and the sensor placement can be arranged.
Buggy build design discussed -
  • Wheel set-up needs further research. We have two wheels to connect to the motors but are missing a third to balance the buggy. We have decided to use a wheel on a pivot but this will depend on availability. Alternatives have been discussed in case a pivot wheel can not be sourced.
  • We have sourced some acrylic that could be used for the buggy chassis.
  • Sandra has sourced some electronic components for soldering to a stripboard circuit on the final build.

Stripboard will need to be sourced.

Tuesday, 16 March 2010

Meeting 3 (16/03/2010)

Basic control program was created and the motor side of the circuit was built. Tasks for the next meeting were set, which included research into industry applications and whether or not too much automation was a good thing.

In the meeting it was decided to use LDR sensors combined with LED backing light. This was because the form A reed switches were dicovered as not being sensitive enough to detect the small field created by the magnetic path.

Next meeting thursday

Monday, 15 March 2010

Meeting 2 (15/03/2010)

Basics designs and program possibilities were discussed and roles were formally assigned.

Assignment of roles
- Project Manager (Programming team): Mark Hawkins
- Assistant Project Manager (Build Team): Sophie Latham
- Lead Programmer: Sandra Donohoe
- Electronics Specialist: Anand Bhana
- Chief Designer: Daljinder Sandhu

By the next meeting member will have completed their individual research and will bring it to the meeting tomorrow.

Meeting 1 (09/03/2010)

In the first meeting the following actions were carried out:

- Transferral of contact details between group members
- Setting up of blog
- Job allocations
- Minutes of meeting