Tuesday 23 March 2010

Project Update (23/03/2010)

The project is ahead of schedule thus far. The Gantt chart below shows the course of the project and that as long as we continue to work effectively, the five day project buffer will not be required.



All research is complete, as well as the designs and program. The prototypes were successfully tested today and plans for the final build of the circuit and buggy were finalised. The circuit components have been sourced and tested, however several buggy components still require sourcing.

In summary, we are ahead of schedule and the tasks remaining involve sourcing the last buggy components, soldering the circuit, and assembling the buggy.

Posted by Mark Hawkins

No comments: